Andrew Needham Chair of CPRE Cheshire writes on raising awareness of the impact of HS2 in the latest edition of Cheshire Viewpoint.

We had an enjoyable walk along the Trent and Mersey Canal to see the impact of HS2. This event raised public awareness and we were pleased that Antoinette Sandbach MP for Eddisbury secured a debate about this issue.

One of the major issues to come out of the debate, which was held in Westminster Hall, was the major problems caused by geotechnical issues on the route chosen by Hs2 Ltd, as highlighted by the Eddisbury MP.

Antoinette Sandbach stated:

“If phase 2b is to go ahead, it is vital that it be done properly. At such a high cost to the taxpayer—£55.7 billion—and with budgets having risen significantly since High Speed 2 was first announced, the route must be designed so as to avoid unnecessary cost to the taxpayer.

The proposed route of HS2 through my constituency of Eddisbury will not only cause significant environmental damage and noise disruption to many areas, but come at a particularly high cost to the taxpayer because of the unique geotechnical challenges of routing HS2 through an area of current and historical salt mining and across land with a long history of significant subsidence risk. HS2’s route through Eddisbury must be looked at again, and the serious and valid concerns raised by independent experts, academics and local people need to be taken into account to find a route that works better both for the local communities and for the taxpayer….

…I also wish to raise the decision last year to realign the route through Eddisbury 800 metres to the west, and the concerns that have been raised about taking it through an area with a greater amount of wet rockhead—unstable ground liable to subsidence as a result of salt. HS2’s decision to move the route came about because the original 2013 proposed route went through the area where the UK’s strategic gas reserves are stored. It was of course practical to move the route away from the gas reserves, but moving it 800 metres to the west has caused other problems, because it still goes through an area with geotechnical challenges that are not easy to engineer around and where there will be a significant cost to the communities and the taxpayer.

TerraConsult Ltd produced an independent geotechnical report on the proposed change of route and concluded that there would be an increase of 11% in the route length over wet rockhead. HS2’s lead ground engineer has called the ground conditions in the Cheshire salt area “spicy”, referring to the engineering challenges of building a high-speed railway line in that area, and HS2’s own consultant, Wardell Armstrong, recognises the risks of building HS2 through Eddisbury in its report on salt-related ground instability. The Government must recognise the risks in the area and move the route away entirely. Alarmingly, before making route choice proposals, HS2 had not done any detailed ground surveys for use as a baseline to track ground movement. As far as I am aware, those surveys have still not been carried out.

The engineering challenges require significantly increased height and length of the embankments and viaducts—up to 26 metres. There will be two additional crossings of the Trent and Mersey canal, one at the location of previous subsidence at Billinge. That comes at an estimated additional cost to the taxpayer of £750 million and significantly increases the noise and visual damage for communities. The route alternatives set out in the TerraConsult report should be looked at and given serious consideration.”

Andrew Needham, Chairman